Materials calculator

Concrete and ballast calculator

Work out how much cement, sand, aggregate or all-in ballast you need for a slab, footing or path. Quantities follow the Concrete Society’s DIY volume-batching table (published 3 June 2025), which assumes 25 kg bags of cement and 20 mm aggregate.

The pour

Enter depth in metres (100 mm is 0.1 m). The 10% waste allowance is a starting point you can change. The Concrete Society table itself has no wastage built in. This is not a structural design.

Common questions

What mix should I use?

The Concrete Society’s DIY volume-batching table (published 3 June 2025) gives three concrete mixes: foundations (footings, blinding, fence posts) at 1:2.5:3.5 or 1:6 all-in ballast; general use (garage, shed base, domestic floors) at 1:2:3 or 1:5 ballast; and paving (paths, drives, steps) at 1:1.5:2.5 or 1:4 ballast. There is also a 1:4 bedding mortar for paving slabs. This is guidance for site mixing, not a structural specification.

How many bags of cement per cubic metre?

In that Concrete Society table, assuming 25 kg bags and 20 mm aggregate: 5 bags per m³ for foundations, 6 for general use, and 8 for paving or bedding mortar. This calculator multiplies those figures by your volume and waste allowance, then rounds bags up for ordering.

Is a 1:4 ballast mix the same thing?

For general-purpose concrete, Hanson / Heidelberg Materials Multicem data sheet gives 1 part cement to 4 parts all-in ballast by volume. The Concrete Society’s paving mix is also 1:4 ballast; its general-use ballast mix is 1:5. Use the mix that matches the job, and treat the quantities as estimates.

Is the waste allowance official?

The quantities in the Society’s table do not include wastage. Tarmac has recommended adding about 10% extra cement when purchasing, and rounding aggregates up. The default 10% here is a starting point you can change, not a requirement.